Algeria

Onshore Gas Plant

Client: National Oil Company

Maintenance, Inspection and Integrity Engineering project.

Staff: 25 people at peak
Duration: 3 years

Brunei

Onshore / Offshore Gas Plant

Client: Major

Turnkey Operation and Maintenance services.

Staff: 50 people on average
Duration: since 1998

Australia

Onshore Gas Liquefaction Plant

Client: Major

Design and implementation of an obsolescence database to ensure facility availability.

Duration: 9 months

Commissioning & Start-Up

Our solutions span from engineering and preparation through to execution, supervision, performance tests, and initial operations.

Commissioning Banner

France

Chemical Plant

Client: Chemical Industrial

Commissioning engineering and execution assistance for a new ABS unit.

Duration: 4 months

Iraq

Onshore Gas Field

Client: International Oil Company

Full-cycle commissioning, start-up, and O&M of a sour gas treatment plant.

Duration: 3 years

Kuwait

Two Refineries

Client: National Oil Company

Commissioning & start-up execution to increase refinery capacity and meet European standards.

Staff: 400 people at peak
Duration: 5 years

Project Engineering & Construction

We manage full EPCCI projects in Electricity, Instrumentation, Automation, and Telecommunications through our dedicated center of excellence.

Engineering Banner

Algeria

Onshore Gas Pipeline

Client: National Oil Company

Upgrade of fiber optic telecommunications and SCADA systems along three major gas pipelines.

Duration: 31 months

Angola

FPSO

Direct: Intl. EPC | Final: Major

Construction engineering and precommissioning for the E&I package of a brownfield FPSO extension.

Duration: 30 months

France

Offshore Wind Farm

Direct: Intl. EPC | Final: Operator

EPCCI of the E&I package for transition pieces of 71 large-scale (7 MW) wind turbines.